UPDATE MARCH 17 4:37 PM:
Great news! Gate testing has been successfully completed! 🎉 Water impounding is kicking off today!
UPDATE MARCH 16 4:48 PM:
Latest Update on Dam Progress:
GBRA has informed us that gate testing will continue tomorrow. We will send another status update by end of day tomorrow.
UPDATE MARCH 13 2:51 PM:
Gate testing is still underway and the contractor is working a few items that need to be addressed prior to gate operations. The current target for impounding water is Tuesday, March 17.
ORIGINAL:
Latest Status on Lake McQueeney Dam progress:
Gate testing began on March 9th and is expected to last for 3-5 days. While this is slightly later than expected, we are almost there! Impounding water will begin when gate testing is complete.