The Board of Directors for Lake McQueeney Water Control and Improvement District No. 1 (LMWCID 1 or the District) would like to provide residents an update on the work performed so far at the dam for the Lake McQueeney Spillgate Replacement and Dam Armoring Project.
Schedule Status
- Substantial completion is still on track for late August 2025
Current Work Status
Electrical demolition within the control building is nearing completion
- Transformer removal is pending
Removal of the Bay 1 concrete obstruction, which blocked the coffer dam sheet piling installation, has been completed
Bay 1 coffer dam sheet piling installation is ongoing
Filling of the south, downstream retaining wall void has commenced
Upcoming work
Bay 1 cofferdam sheet piling installation completion
Dewatering of Bay 1 cofferdam and excavation between the dam and Bay 1 cofferdam
Below, find updated pictures of the work being performed.
If residents have additional questions regarding the Lake McQueeney Spillgate Replacement and Dam Armoring Project, please use the “Contact Us” form on the District website.